78 Guestrooms. 3 Corridors, Public space, Lobby, Meeting Room, Fitness Room, Public restrooms, Pool area.
Start of work: November 18, 2024
Completion of work: March 26, 2025
Guest Room Renovation Scope:
- Prep & paint ceilings
- Prep & paint door frames
- Replace carpet
- Install wallpaper
- Reinstall furniture to original locations
Bathrooms Renovation Scope:
- Install wallpaper
- Prep and paint ceilings
- Remove existing bathtub and install new bathtub
- Tub surrounds installation
Corridor Renovation Scope:
- Install wallpaper
- Prep and paint ceilings
- Carpet replacement
- Light fixture installation
Public space, Lobby, Breakfast area:
- Install wallpaper
- Prep and paint ceilings
- Carpet replacement
- Light fixture installation
- Furniture installation
- Artwork installation
Tub surround installation
Fitness room Renovation Scope:
- install rubber flooring
- Prep & Paint Walls and Ceiling
Pool area:
- Prep & Paint Walls and Ceiling